Capital Budgeting Tools
					
						Created by David Moore, PhD
					
                    
                     Reference Material: Chapter 9 of Textbook
				
				
                
					Key Concepts
                   
					
                        - Net Present Value (NPV)
 
                        - Payback Period
 
                        - Internal Rate of Return (IRR)
 
                        - Investment criteria (accept/reject decision)
 
                        - Mutually Exclusive Projects and Non-conventional cash flows
 
                    
                    
				
                
                
                
                
                    Personal Capital Budgeting Examples
                    
                    - Graduate School
 
                        
                            - How expensive is grad school?
 
                            - How long will it take?
 
                            - How much more will I make with a grad degree?
 
                            - What are the opportunity costs of wages while in grad school?
 
                        
                    - Repair or Replace Car
 
                        
                            - How expensive is new car?
 
                            - How much are my expected repair bills going to be with the old car?
 
                            - How long before the old car is inoperable?
 
                        
                    
                
                   
                   
                    Capital Budgeting Tesla Example
                       
  
                       
                   
                   
                   
                    Example: College cash flows 
                       
                       
                       - Average costs to attend a 4 year public university in the U.S. have risen from about $\$$27,161 in 1996 to about $\$$39,529 in 2016. 
 
                           - As of 2018, the average annual earnings for a high school graduate were $\$$35,256. The average starting annual earnings for a college graduate with a business degree were $\$$62,000. For simplicity, let's ignore taxes and just assume these are all after-tax cash flows.  
 
                           - Assume that you complete the degree in 4 years. You work for 45 years after attaining your degree and college salary grows at 3% annually. All cash flows occur at the end of the period (e.g. no outflows at t=0).  
 
                       
                           We will come back to this and use investment criteria to make decision. 
                       
                   
                   
                   
                    Key points
                       
                        - Analysis of potential projects
 
                           
                            - Fixed Asset
 
                            - New product
 
                            - Enter new market
 
                           
                        - Long-term decisions
 
                        - Large expenditures
 
                        - Difficult/impossible to reverse
 
                        - Determines firm's strategic direction
 
                       
                 
                
                   
                   
                       
                       
                       
                        Good Decision Criteria
                           
                           - All cash flows considered?
 
                           - TVM considered?
 
                           - Risk-adjusted?
 
                           - Ability to rank projects?
 
                           - Indicates added value to the firm?
 
                         
                       
                       
                       
                            Tools
                           
                            - Net Present Value (NPV)
 
                            - Payback Period
 
                            - Internal Rate of Return
 
                           
                       
                       
                       
                            Sample Project
                           You are looking at a new project and have estimated the following cash flows, net income and book value data:
                           
                           
                           
                            
                            | Year |    
                            Cash Flow | 
                            
                               
                               | 0 | 
                                -165,000 | 
                               
                               
                                | 1 | 
                                63,120 | 
                               
                               
                               | 2 | 
                                70,800 | 
                               
                               
                               | 3 | 
                                91,080 | 
                               
                               
                            
                           
                           
                           Required return = 12%
                           This project will be the example for all problem exhibits in this chapter.
                           
                           
                       
                       
                   
                
                
                    
                    
                        Overview
                        	How much value is created from undertaking an investment?
                        
                        
                        - Estimate the expected future cash flows.
 
                        - Estimate the required return for projects of this risk level.
 
                            - Find the present value of the cash flows and subtract the initial investment to arrive at the Net Present Value.
 
                        
                        
                    
                    
                    
                        Calculation
                        
                        $$NPV=\sum_{t=0}^n \frac{CF_t}{(1+r)^t}$$
                        
                        Initial cost is often $CF_0$ and is an outflow.
                        
                        $$NPV=\sum_{t=1}^n \frac{CF_t}{(1+r)^t}-CF_0$$
                    
                        
                    
                        Decision Rule
                        If NPV is positive, accept the project
                        
                        - What does a positive NPV mean?
 
                            
                                - Project is expected to add value to the firm
 
                                - Will increase the wealth of the owners
 
                            
                            - NPV is a direct measure of how well this project will meet the goal of increasing shareholder wealth.
 
                        
                        
                    
                    
                    
                        NPV for Sample Project
                        
                        $$NPV=\sum_{t=0}^n \frac{CF_t}{(1+r)^t}$$
                        
                                                  
                           
                            
                            | Year |    
                            Cash Flow | 
                            Formula | 
                            Discounted CF | 
                            
                               
                               | 0 | 
                                -165,000 | 
                                =(-165000)/1.12^0  | 
                                -165,000.00 | 
                               
                               
                                | 1 | 
                                63,120 | 
                                =(63120)/1.12^1 | 
                                56,357.14 | 
                               
                               
                               | 2 | 
                                70,800 | 
                                =(70800)/1.12^2 | 
                                56,441.33 | 
                               
                               
                               | 3 | 
                                91,080 | 
                                =(91080)/1.12^3 | 
                                64,828.94 | 
                               
                               
                               
                                | 
                                    | 
                                        NPV = | 
                                   12,627.41 | 
                               
                               
                            
                           
                           
 
                    
                    
                    
                    
                        Excel
                        =NPV(rate,$CF_1-CF_t$)
                       
                            - First parameter = required return entered as a decimal
 
                            - Second parameter = range of cash flows beginning with year 1
 
                            - After computing NPV, subtract the initial investment ($CF_0$)
 
                        
                        
 
                    
                    
                    
                        Rationale
                        
                        - NPV =  PV inflows – Cost 
 
                        - NPV=0 → Project's inflows are "exactly sufficient to repay the invested capital and provide the required rate of return"
 
                        - NPV = net gain in shareholder wealth
 
                        
                        
                    
                    
                    
                        Decision Rule
                        
                        Accept Project if NPV > 0
                    
                    
                    
                        Pros and Cons
                        
                        - Pros
 
                            
                                - Meets all desirable criteria
 
                                    
                                        - Considers all Cash Flows
 
                                        - Considers Time Value of Money
 
                                        - Adjusts for risk
 
                                        - Can rank mutually exclusive projects
 
                                    
                                - Directly related to firm value
 
                                - Dominant method; always prevails
 
                            
                        - Cons
 
                            
                                - relies heavily on correct discount rate
 
                            
                        
                    
                    
                    
                
                
                
                    
                    
                    
                        Overview
                        How long does it take to recover the initial cost of a project?
                        Computation
                        
                            - Estimate cash flows
 
                            - Subtract the future cash flows from the initial cost until initial investment is recovered
 
                        
                        
                        
                        - A "break-even" type measure
 
                        
                    
                    
                    
                        Computing Payback
                                                                          
                           
                            
                            | Year |    
                            Cash Flow | 
                            Cumulative Cash Flows | 
                            
                               
                               | 0 | 
                                -165,000 | 
                                -165000  | 
                               
                               
                                | 1 | 
                                63,120 | 
                                -101,880 | 
                               
                               
                               | 2 | 
                                70,800 | 
                                -31,080 | 
                               
                               
                               | 3 | 
                                91,080 | 
                                60,000 | 
                               
                               
                               
                               | Payback = | 
                                    2 + 31080/91080 | 
                                   2.34 years | 
                               
                               
                            
                           
                           
                        Payback = 2 + $\frac{31080}{91080}$=2.34 years
                        
                        Do we accept or reject the project?
                    
                    
                    
                        Decision Rule
                        
                        Accept if the payback period is less than some preset limit
                    
                    
                    
                        Pros and Cons
                        
                        
                        
                            
                            
                                Advantages
                                
                                    - Easy to understand
 
                                    - Adjusts for uncertainty of later cash flows
 
                                    - Biased towards liquidity
 
                                    - Good for small projects
  ($\$$10000)
                                
                             
                            
                            
                                Disadvantages
                                
                                - Ignores the time value of money
 
                                - Requires an arbitrary cutoff point
 
                                - Ignores cash flows beyond the cutoff date
 
                                - Biased against long-term projects, such as research and development
 
                                
                             
                        
                         
                            ASKS THE WRONG QUESTION!
                    
                
                
                    
                
                
                    
                        Internal Rate of Return (IRR)
                    
                    
                    
                        Overview
                        
                            - Most important alternative to NPV
 
                            - Widely used in practice 
 
                            - Intuitively appealing
 
                            - Based entirely on the estimated cash flows 
 
                            - Independent of interest rates
 
                        
                        
                    
                    
                    
                        Definition
                        IRR = discount rate that makes the NPV = 0
                        Enter NPV = 0, solve for IRR:
                        $$NPV=\sum_{t=0}^n \frac{CF_t}{(1+r)^t}$$
                    
                    
                    
                        Computing IRR
                        
                            - Without a financial calculator or Excel, this becomes a trial-and-error process
 
                            - Excel
 
                            
                            
                                - =IRR($CF_0-CF_t$, guess)
 
                                - Guess option useful for when multiple IRRs exist
 
                         
                            
                            
                        
                    
                    
                        Decision Criteria
                        
                        Accept the project if the IRR is greater than the required return
                    
                    
                        Example
                                                   
                           
                            
                            | Year |    
                            Cash Flow | 
                                
                            
                               
                               | 0 | 
                                -165,000 | 
                               
                               
                                | 1 | 
                                63,120 | 
                               
                               
                               | 2 | 
                                70,800 | 
                               
                               
                               | 3 | 
                                91,080 | 
                               
                               
                             | =IRR($CF_0:CF_3$) |   
                            16.13% | 
                            
                            
                           
                           
                        
                        Accept or Reject?
                    
                    
                    
                        NPV Profile
                        
 
                    
                    
                    
                        Pros and Cons
                        
                        
                        
                            
                            
                                Advantages
                                
                                    - Intuitively appealing/Easy to communicate the value of a project 
 
                                    - If the IRR is high enough, may not need to estimate a required return
 
                                    - Considers all cash flows
 
                                    - Considers time value of money
 
                                    - Provides indication of risk
 
                                
                             
                            
                            
                                Disadvantages
                                
                                - Can produce multiple answers
 
                                - Cannot rank mutually exclusive projects
 
                               
                                
                             
                        
                         
                          
                    
                
                    
                
                    
                
                    Summary of Decisions
                                                                       
                           
                            
                            | Method |    
                            Criteria | 
                                Number | 
                                Decision | 
                                
                            
                               
                               | NPV | 
                                NPV$>$0 | 
                                12,627.41 | 
                                   Accept | 
                               
                               
                                | Payback | 
                                Unknown | 
                                   2.34 years | 
                                   ??? | 
                               
                               
                               | IRR | 
                                IRR$>$Required Return | 
                                   16.13% | 
                                Accept | 
                               
               
                            
                           
                           
                
                
                
                    
                    
                    
                        Overview
                        
                        - NPV and IRR will generally give the same decision
 
                        - Exceptions
 
                            
                            - Non-conventional cash flows 
 
                            
                                - Cash flow sign changes more than once
 
                            
                            - Mutually exclusive projects
 
                                
                                - Initial investments are substantially different
 
                                - Timing of cash flows is substantially different
 
                                - Will not reliably rank projects
 
                                
                            
                        
                    
                    
                    
                        Non-Conventional Cash Flows
                        Cash flows change sign more than once
                        
                        - Produces more than one IRR
 
                        - Which one do you use to make your decision?
 
                        
                    
                    
                    
                        Example
                        Suppose an investment will cost $\$$90,000 initially and will generate the following cash flows:
                        
                        
                            - Year 1: 132,000
 
                            - Year 2: 100,000
 
                            - Year 3: -150,000
 
                        
                        
                        The required return is 15%.
                        Should we accept or reject the project?
                    
                    
                    
                       Summary
 
                        
                            
                                | Year | 
                                Cash Flow | 
                            
                            
                                | 0 | 
                                -90,000 | 
                            
                            
                                | 1 | 
                                132,000 | 
                            
                            
                                | 2 | 
                                100000 | 
                            
                            
                                | 3 | 
                                -150000 | 
                            
                        
                        
                            
                                | Investment Criteria | 
                                
                            
                            
                                | NPV | 
                                1,769.54 | 
                            
                            
                                | IRR-1 | 
                                10.11% | 
                            
                            
                                | IRR-2 | 
                                42.66% | 
                            
                        
 
                        NPV says Accept
                        IRR-1 says Reject
                        IRR-2 says Accept
                        
                        
                    
                    
                    
                        NPV Profile
                        
 
                        When you cross the x-axis more than once, there will be more than one return that solves the equation
                    
                    
                        Independent versus Mutually Exclusive Projects
                        
                            - Independent
 
                            
                            - The cash flows of one project are unaffected by the acceptance of the other.
 
                            
                            - Mutually Exclusive 
 
                            
                            - The acceptance of one project precludes accepting the other. 
 
                            
                        
                        NPV should be used to choose between mutually exclusive projects.
                    
                    
                    
                    
                        Example
                        Which project should you accept if the required return is 10% and the you can only finance one project.
                           
                           
                            
                            | Period |    
                            Project A | 
                                Project B | 
                                
                            
                               
                               | 0 | 
                                -500 | 
                                -400 | 
                                
                               
                               
                                | 1 | 
                                325 | 
                                   325 | 
                               
                               
                               | 2 | 
                                325 | 
                                   200 | 
                               
                               
                               
                                | IRR | 
                                19.43% | 
                                22.17% | 
                               
                               
                                | NPV | 
                                64.05 | 
                                60.74 | 
                               
             
                            
                           
                           
                        
                    
                    
                    
                        Graph: Crossover Rate
                        
 
                    
                    
                    
                        Finding Crossover Rate
                        
                                                   
                           
                            
                            | Period |    
                            Project A | 
                                Project B | 
                               Difference | 
                                
                            
                               
                               | 0 | 
                                -500 | 
                                -400 | 
                                   -100 | 
                                
                               
                               
                                | 1 | 
                                325 | 
                                   325 | 
                                   0 | 
                               
                               
                               | 2 | 
                                325 | 
                                   200 | 
                                   125 | 
                               
                                                                                      
                               
                                | IRR | 
                                19.43% | 
                               22.17% | 
                                11.80% | 
                               
                        
                              
                                        
                    
                    
                    
                    
                        Crossover Rate Graph Example 2
                        
 
                    
                    
                    
                        Conflicts Between NPV and IRR
                        
                            - NPV directly measures the increase in value to the firm
 
                            - Whenever there is a conflict between NPV and another decision rule, always use NPV
 
                            - IRR is unreliable in the following situations:
 
                            
                                - Non-conventional cash flows
 
                                - Mutually exclusive projects
 
                            
                        
                    
                    
                
                    
                    
                    
                
                                     Other capital budgeting tools 
                (we will ignore these, know that they exist)
                    
                    - Modified Internal Rate of Return (MIRR)
 
                        - Average Accounting Return
 
                        - Discounted Payback
 
                        - Profitability Index
 
                    
   
                
                   
                
                    
                
                    Capital budgeting importance
  
                    
 
                
            
                
                    What Do Manager's Do?
   
                    
 
                
                
                    Why is IRR popular?
                    
                        - People like rates instead of dollars.
 
                        - "Remodeling the clerical wing has a 20% return"
 
                        - "At a 10% discount rate, the net present value is $\$$4,000."
 
                    
                
                
                    Summary
 
                    
                        - Consider all investment criteria when making decisions
 
                        - NPV and IRR are the most commonly used primary investment criteria
 
                        - Payback is a commonly used secondary investment criteria
 
                        - All provide valuable information
 
                    
                
                        
                    
                    
                        
                        
                            NPV
                            
                                - NPV= Difference between market value (PV of inflows) and cost
 
                                - Accept if $NPV>0$
 
                                - No serious flaws
 
                                
                                    - Does require an appropriate discount rate
 
                                
                                - Preferred decision criterion
 
                            
                        
                        
                        
                            Payback
                            
                                - Payback = Length of time until initial investment is recovered
 
                                - Accept if payback $<$ some specified target
 
                                - Doesn't account for time value of money 
 
                                - Ignores cash flows after payback
 
                                - Arbitrary cutoff period
 
                                - Asks the wrong question
 
                            
                        
                        
                        
                            IRR
                            
                                - IRR = Discount rate that makes NPV = 0 
 
                                - Accept if IRR > required return
 
                                - Same decision as NPV with conventional cash flows
 
                                - Does not require a discount rate
 
                                - Unreliable with:
 
                                
                                    - Non-conventional cash flows 
 
                                    - Mutually exclusive projects
 
                                
                                - MIRR = better alternative (NOT COVERED)
 
                            
                        
                    
                       
                
                  
                    
                        Example 1
                        Consider an investment that costs $\$$100,000 and has a cash inflow of $\$$25,000 every year for 5 years. The required return is 9% and required payback is 4 years.
                        
                            - What is the payback period?
 
                            - What is the NPV?
 
                            - What is the IRR?
 
                            - Should we accept the project?
 
                            - What decision rule should be the primary decision method?
 
                            - When is the IRR rule unreliable?
 
                        
                    
                    
                    
                        Solution
                        
 
                    
                    
                    
                        Example 2
                        Benny's is considering adding a new product to its lineup. This product is expected to generate sales for four years after which time the product will be discontinued. What is the project's net present value if the firm wants to earn a 14 percent rate of return?
                        
                            
                                | Year | 
                                Cash Flow | 
                            
                            
                                | 0 | 
                                -65,000 | 
                            
                            
                                | 1 | 
                                16,500 | 
                            
                            
                                | 2 | 
                                23,800 | 
                            
                            
                                | 3 | 
                                27,100 | 
                            
                            
                                | 4 | 
                                23,300 | 
                            
                        
                        What is the IRR?
                        
                        What is the payback?
                    
                    
                
                    
                
                    Revisit College Decision
                    
 
                
                    
                
                    Car Lease vs Buy Example
    
                    
 
                
                    
                 
                    
                Key Learning Outcomes
                    
                        - Calculate: NPV, Payback Period, IRR
 
                        - Make Capital budgeting decision (Decision rule: accept/reject)
 
                        - Pros and cons of NPV, payback, IRR
 
                        - Issues with:
 
                        
                        - Mutually exclusive projects
 
                        - Unconventional cash flows